Dec 02

December Construction

Posted on December 2, 2016 at 9:31 AM by Planning Department

Grading of the trail will begin between Dunk & Bubble and the Route 2A Bridge.  2A bridge work will continue; the bridge deck is expected to be poured this month as weather permits.
Nov 09

Installation of Steel Bridge on Route 2A

Posted on November 9, 2016 at 11:45 AM by Planning Department

Route 2A / Great Road will be closed on Sunday November 13th through Thursday November 17th between the hours of 10:00PM & 5:00AM to erect the steel bridge. A detour route will be located on Main Street to Brook Street.

Apr 27

April 27, 2016 Update

Posted on April 27, 2016 at 10:43 AM by Planning Department

Rte. 2A Bridge Drill Shaft Piers:
Construction of the two drilled shaft piers for the pedestrian bridge over Rte. 2A were completed last week.

Upcoming Work for May:
- Sand blasting and painting the six existing bridges
- Possibly construction of the MSE walls at the Rte.2A crossing